Solar Park Kosuriq ready for ERO Board Authorization

Shkruar nga

në

18.07.2026, Prishtina

Following the submission of the Application for Authorization for the Construction of New Generation Capacities for the 99 MWAC Solar Park in Kosuriq on 19 June 2026, the Energy Regulatory Office (ERO) completed its review of the application and supporting documentation. Subsequent to the settlement of the required administrative authorization fee and the completion of the mandatory public notice period published in two local daily newspapers on 10 July 2026 (spanning eight calendar days) with no public objections, inquiries, or complaints received, the application is deemed administratively complete and submitted for ERO Board review and final authorization decision

ERO announcement:

https://www.ero-ks.org/zrre/sq/njoftimi-publik-aplikacioni-autorizim-solariss-llc

Announcement:

https://solariss.llc/uncategorized/njoftim-publik-autorizim/